Subject: [SLR-Mail] No.2839: 7824 SFEL: Planned Schedule - Improvement works From: =?iso-8859-1?Q?Manuel_S=E1nchez_Piedra?= Author: Manuel A. Snchez Piedra After successfully completing the infrastructure works on the dome of the main building of our Observatory, I share with you the planned schedule that affects San Fernando laser station in the coming months. Final phase of the mount replacement project: - Factory Acceptance Test: May to June. - Shipping and planned to complete the installation on June 21st. - Site Acceptance Test: until the final delivery date planned on July 12th. Best regards, Manu ____________________________ Lt Cdr. Manuel Angel Sanchez Piedra Head of San Fernando Laser Station Royal Observatory of Spanish Navy Tel.: +34 956-545607 Email: msanpie@roa.es ____________________________

Author: Manuel A. Snchez Piedra

 

After successfully completing the infrastructure works on the dome of the main building of our Observatory,

I share with you the planned schedule that affects San Fernando laser station in the coming months.

 

Final phase of the mount replacement project:

- Factory Acceptance Test: May to June.

- Shipping and planned to complete the installation on June 21st.

- Site Acceptance Test: until the final delivery date planned on July 12th.

 

Best regards,

Manu

____________________________

 

Lt Cdr. Manuel Angel Sanchez Piedra

Head of San Fernando Laser Station

Royal Observatory of Spanish Navy

Tel.: +34 956-545607

Email: msanpie@roa.es

____________________________